Construction manager at risk (CMAR) is a project delivery method in which the owner hires a construction manager during design, uses that firm’s estimating and scheduling advice while the drawings develop, and then has the same firm build the project under a guaranteed maximum price (GMP). The construction manager holds the trade contracts and carries the risk of costs above the GMP, except for changes the owner makes to the scope.

The method sits between the two most familiar approaches. Like design-bid-build, the owner keeps a separate contract with the architect or engineer. Like design-build, the builder joins early. This guide explains how a construction manager at risk is selected, what happens in each phase, how the GMP is built, and how to tell whether the method fits your project.

Construction Manager at Risk at a Glance

  • Contracts: two. Owner and designer; owner and construction manager.
  • When the builder joins: during design, often at or before schematic design.
  • How the builder is chosen: mostly on qualifications, experience, and fees rather than a lump-sum bid.
  • How price is set: a negotiated guaranteed maximum price once the design is far enough along.
  • Who holds the trade contracts: the construction manager, who usually bids them out competitively.
  • Common uses: schools, hospitals, public buildings, renovations of occupied facilities, and complex or phased industrial work.
Finished industrial building with equipment working in the yard on a Doss and Horky project, illustrating construction manager at risk delivery

What Is Construction Manager at Risk?

A construction manager at risk is a contractor who acts as the owner’s construction advisor during design and as the builder during construction. The “at risk” part refers to the firm’s financial commitment. Once the GMP is signed, the construction manager is responsible for delivering the agreed scope for no more than that price. If the work costs more, the construction manager absorbs the overrun. If it costs less, the contract decides how the savings are split or returned.

The method goes by several names. CM at risk, CMAR, and CM-at-risk are the most common. Transportation agencies often call a similar approach CM/GC, for construction manager/general contractor. All of them share the same core idea: early contractor input followed by a negotiated price.

What does “at risk” actually mean?

It means the construction manager’s own money is on the line above the GMP. The owner still pays for scope changes it requests, unforeseen conditions the contract assigns to the owner, and items the contract excludes. Everything else needed to build what the GMP documents describe is the construction manager’s responsibility. That is why GMP negotiations focus so heavily on what the drawings show and what assumptions sit behind the number.

How CMAR Compares to Other Delivery Methods

Our delivery method comparison covers design-bid-build, design-build, and CM at Risk side by side. Here is the short version, focused on what changes for the owner.

Design-bid-buildConstruction manager at riskDesign-build
Owner contractsDesigner and contractorDesigner and construction managerOne design-build entity
Builder joinsAfter design is completeDuring designAt the start
How builder is selectedLowest responsive bidQualifications and feesQualifications, price, or both
Price setAt bidGMP, negotiated during or after designEarly, as lump sum or GMP
Owner’s design controlHighHighLower
Overlap of design and constructionNoneSome, through early packagesMost

Construction manager at risk vs. agency construction manager

An agency construction manager, sometimes called CM agency or CM as advisor, works for a fee and gives advice. It doesn’t hold the trade contracts or guarantee a price. The owner contracts directly with the trades or a general contractor, and the owner keeps the cost risk. A construction manager at risk does both jobs: it advises during design and then guarantees the price and builds.

Construction manager at risk vs. general contractor

In design-bid-build, a general contractor prices a finished design and is usually chosen by low bid. It has no role in shaping the design. A construction manager at risk joins earlier, is chosen mainly on qualifications, and helps shape the design before committing to a price. Our guide to what a general contractor does covers the general contractor’s role in more detail.

How Construction Manager at Risk Works: 7 Steps

1. The owner hires the designer

The owner selects an architect or engineer and starts programming and schematic design. The designer works for the owner, not the construction manager, which is how the owner keeps direct control over design decisions.

2. The owner selects the construction manager at risk

Selection usually starts with a request for qualifications, followed by a request for proposals to a short list and interviews. Owners weigh experience on similar projects, the proposed team, safety record, preconstruction approach, and fees. The fee proposal typically covers the preconstruction fee, the construction fee as a percentage of the cost of the work, and the general conditions, which are the construction manager’s site staff, temporary facilities, and similar costs.

Because the full design doesn’t exist yet, there is no total construction price to compare at this stage. That’s the biggest difference from low-bid selection.

3. Preconstruction services run alongside design

This is where the method earns its keep. While the designer develops the drawings, the construction manager provides:

  • Cost estimates at each design milestone, so the owner sees budget problems while they’re still cheap to fix.
  • Constructability reviews that flag details that will be hard, slow, or expensive to build.
  • Value analysis that compares materials and systems on cost, schedule, and life-cycle performance.
  • Scheduling and phasing, especially important when a building stays occupied or a plant keeps running.
  • Site logistics for access, laydown, deliveries, and work around live operations.
  • Long-lead procurement advice on equipment and materials that need early orders.
Large prepared concrete foundation pad on an industrial site with a tall plant building behind it, on a Doss and Horky project

4. The GMP is negotiated

When the design is far enough along, often somewhere in the construction documents phase, the construction manager prices the work and proposes a GMP. The owner and design team review it, question assumptions, and negotiate. The final GMP becomes an amendment to the construction manager’s contract.

On fast-track projects, the work can be split into packages with separate GMPs. Site work, foundations, or structural steel may start under an early package while the rest of the building is still being designed.

5. The construction manager bids the trade work

The construction manager breaks the work into trade packages, such as earthwork, concrete, steel, roofing, mechanical, and electrical, and solicits bids from subcontractors. Public owners often require this bidding to be open and advertised. Some contracts let the construction manager self-perform certain work, sometimes only if its price competes against outside bids. The rules belong in the contract.

6. Construction

The construction manager builds the project much as a general contractor would: running the site, the schedule, safety, quality, and the subcontractors. The difference is that cost reporting is usually open-book. The owner can see actual costs against the GMP, and the contract typically gives the owner audit rights.

7. Closeout and reconciliation

At the end, the construction manager closes out the subcontracts, delivers warranties and as-built documents, and reconciles final costs against the GMP. Any unused contingency and savings are handled according to the contract, either returned to the owner in full or shared between owner and construction manager.

What Goes Into a Guaranteed Maximum Price

A GMP is more than a single number. Owners should understand each piece.

GMP componentWhat it covers
Cost of the workSubcontracts, self-performed labor, materials, and equipment
General conditionsProject manager, superintendent, field office, temporary utilities, cleanup, and similar site costs
Construction manager’s feeOverhead and profit, usually a percentage of the cost of the work
Construction manager’s contingencyA reserve for risks the construction manager carries, such as estimating gaps and coordination issues
AllowancesSet amounts for items not fully designed yet, adjusted when the item is defined
Insurance and bondsBuilder’s coverage and performance and payment bonds, where required

The owner usually keeps its own separate contingency for scope changes and unknowns the contract assigns to the owner. How the construction manager’s contingency can be used, and who gets the leftover, are some of the most negotiated terms in any CMAR contract.

Standard contract forms exist for this arrangement. AIA Document A133 covers an owner and construction manager at risk where the basis of payment is the cost of the work plus a fee with a GMP. ConsensusDocs 500 is a similar form. The Associated General Contractors of America is a founding member of the ConsensusDocs coalition and publishes resources on project delivery.

Advantages of Construction Manager at Risk

Early builder input. The construction manager’s estimates and constructability reviews shape the design before it’s locked in, so fewer problems surface in the field.

Cost certainty before construction. The owner knows the maximum price before the bulk of the work starts and has seen how that price was built.

Owner keeps design control. The designer still works directly for the owner.

Selection on qualifications. Owners can pick the team they trust for a complex project rather than the lowest number.

Schedule overlap. Early packages let site work or long-lead items start before the full design is complete.

Transparency. Open-book accounting shows actual costs, and contracts often return unused contingency to the owner.

Disadvantages and Risks to Plan For

The GMP carries contingency. Because the price is set before the design is complete, the construction manager builds in contingency for the unknowns. If the design is very early, that contingency can be large.

Less price competition at the prime level. The construction manager isn’t chosen by low bid, so owners rely on trade bidding, fee competition, and open-book review to keep costs in check.

Scope disputes. Arguments over whether an item was “in the GMP” or a change are the most common CMAR friction. Clear GMP documents, with a list of the drawings, specifications, assumptions, and exclusions behind the number, reduce them.

Design responsibility stays with the designer. The construction manager reviews the design for constructability, but it doesn’t take over the designer’s responsibility for it. Gaps between what the drawings show and what the building needs still land with the owner.

More owner involvement. CMAR works best when the owner has staff or an owner’s representative who can make decisions during design and review cost reports.

When Construction Manager at Risk Fits

CMAR tends to fit projects where early contractor knowledge pays off and the owner wants to keep design control:

  • Renovations and additions to occupied buildings, such as schools, hospitals, and offices, where phasing and logistics drive the cost.
  • Complex buildings with heavy mechanical, electrical, or process systems.
  • Fast-track schedules that need site work or long-lead equipment to start before design is finished.
  • Public projects where the owner wants qualifications-based selection and state law allows it.
  • Industrial expansions next to running operations, where constructability and shutdown planning matter as much as the building itself.

It’s usually a weaker fit for small, simple projects with a fully defined scope, where a straightforward bid gives a competitive price with less overhead, and for owners without the time or staff to stay involved during design.

Interior of a new steel-framed building with a metal deck mezzanine and stairs under construction, built by Doss and Horky

Can public owners use CMAR?

Many can, but only where state law and their own procurement rules allow it. States differ on which agencies may use the method, how the construction manager is selected, whether trade packages must be publicly bid, and whether the construction manager may self-perform work. Kentucky school districts, cities, counties, and state agencies should confirm the rules that apply to them with their counsel and procurement office before choosing a delivery method.

Questions to Ask Before You Sign a CMAR Contract

  • When will the GMP be set, and at what design stage?
  • What exactly is in the GMP documents, and which assumptions and exclusions sit behind the number?
  • How can the construction manager’s contingency be used, and who keeps what’s left?
  • How will savings be shared?
  • How will trade packages be bid, and may the construction manager self-perform work?
  • What does the preconstruction fee include, and what happens if the project stops before a GMP is agreed?
  • What cost reports will the owner see, and how often?
  • What audit rights does the owner have?

A CMAR contract is a significant legal document. Have it reviewed by counsel familiar with construction before signing.

How Doss and Horky Delivers Projects

Doss and Horky’s General Contracting Division has built industrial, commercial, municipal, and distillery projects across Kentucky since 1985, using design-build, competitively bid general contracting, and construction management. Whatever the contract structure, the work starts with preconstruction: estimates, constructability reviews, and logistics planning, so the owner sees cost and schedule problems on paper rather than in the field.

Interior of a building nearing completion with electrical panels on the wall and glass doors to the outside, a Doss and Horky project

Construction Manager at Risk FAQ

What is construction manager at risk?

Construction manager at risk is a delivery method in which the owner hires a construction manager during design for estimating and constructability advice, then has that firm build the project under a guaranteed maximum price. The construction manager holds the trade contracts and covers costs above the GMP except for owner scope changes.

What does a construction manager at risk do?

During design, it provides cost estimates, constructability reviews, scheduling, phasing, and procurement advice. After the GMP is signed, it bids and manages the trade contracts and builds the project, much like a general contractor, with open-book cost reporting to the owner.

What is the difference between a construction manager and a construction manager at risk?

An agency construction manager advises the owner for a fee but doesn’t hold trade contracts or guarantee a price, so the owner keeps the cost risk. A construction manager at risk also advises during design, then commits to a GMP, holds the trade contracts, and carries the risk of overruns.

What is a GMP in construction?

A guaranteed maximum price is a cap on what the owner pays for a defined scope. It includes the cost of the work, general conditions, the contractor’s fee, contingency, and allowances. Costs above the GMP are the contractor’s responsibility unless the owner changes the scope.

How is a construction manager at risk selected?

Usually through a request for qualifications, then a request for proposals to a short list, followed by interviews. Owners compare experience, team, safety, preconstruction approach, and fees rather than a total construction price, because the design isn’t finished yet.

Is CMAR the same as design-build?

No. In design-build, one entity holds both design and construction under a single contract. In CMAR, the owner keeps separate contracts with the designer and the construction manager, so the owner retains more direct control over the design.

When is the GMP set on a CMAR project?

Often during the construction documents phase, once the design is detailed enough to price with reasonable confidence. On fast-track projects, early packages such as site work or steel may get their own GMPs before the rest of the design is complete.

Is construction manager at risk more expensive?

Not necessarily. The GMP includes contingency and a negotiated fee, but early constructability input, competitive trade bidding, and fewer field changes can offset that. Owners often get unused contingency back. Whether it costs more depends on the project, the design stage at GMP, and the contract terms.

Choosing a Delivery Method for Your Next Project

The right delivery method depends on what matters most to you: design control, early cost certainty, speed, or the lowest bid price. If you’re weighing construction manager at risk against design-build or a traditional bid for a project in Kentucky, talk with Doss and Horky’s General Contracting Division before design gets far along, while the delivery method can still shape the project. Read our delivery method comparison or call 859-236-2690.

_This article is general information, not legal or procurement advice. Contract terms and public procurement rules vary; consult your counsel before choosing a delivery method or signing a contract._